HB 344: HSEO; DOT; DAGS; Electric Vehicle Charging Infrastructure; State Buildings; Retrofitting; Appropriation
- Session Year: 2025-2026
- House: House
- Latest Version Date: 2025-04-04
Current Status:
Failed
(2026-04-23: Received notice of appointment of House conferees (Hse. Com. No. 817).)
Introduced
In Committee
First Chamber
In Committee
Second Chamber
Final Decking
Enacted
Requires the design of all new state building construction where parking is to be included to provide that a number of the parking stalls, as determined by the Department of Accounting and General Services, shall be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (SD2)
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (SD1)
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (HD1)
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds.
|
HOUSE OF REPRESENTATIVES |
H.B. NO. |
344 |
|
THIRTY-THIRD LEGISLATURE, 2025 |
H.D. 1 |
|
|
STATE OF HAWAII |
S.D. 2 |
|
|
|
|
|
|
|
||
|
|
||
A BILL FOR AN ACT
RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The legislature finds that the adoption of electric vehicles in the State continues to grow at increasing rates, with electric vehicles accounting for fifteen per cent of all new car sales in 2024, up 11.5 per cent from the year prior. There is a need for charging infrastructure to support this growth and ensure that there is an equitable transition to clean transportation.
The legislature further finds that providing electric vehicle charging options at workplaces is beneficial for several reasons. Workplace charging provides options for people who may not be able to charge at home--typically renters, those who live in apartments, and low- and moderate-income families--the opportunity to participate in the savings and other benefits of owning an electric vehicle. Workplace charging also encourages daytime charging, which benefits the grid by shifting energy use from peak evening hours to daytime hours, when energy is cheaper and cleaner.
Therefore, the legislature finds that there is a need for more workplace charging and that the State should expand workplace charging availability in state facilities.
The purpose of this Act is to:
(1) Require the design of all new state building construction where parking is to be included to provide that a number of the parking stalls, as determined by the department of accounting and general services, shall be electric vehicle charger‑ready;
(2) Require the Hawaii state energy office to conduct a survey and identify certain high-priority state facilities that include parking, including state-owned parking lots that serve a state facility, regardless of whether they are attached to the facility, to be retrofitted to include electric vehicle charging infrastructure;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the Hawaii state energy office to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
SECTION 2. Section 107-27, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows:
"(d) Beginning July 1, 2023, where feasible and cost‑effective, the design of all new state building construction shall:
(1) Maximize energy and water efficiency measures;
(2) Maximize energy generation potential; and
(3) Use building materials that reduce the carbon footprint of the project.
Beginning July 1, 2026, the design of all new state building construction where parking is to be included shall provide that a number of the parking stalls, as determined by the department of accounting and general services, shall be electric vehicle charger-ready.
For the purposes of this subsection, "electric vehicle charger-ready" means having sufficient wiring conduits, raceways, and termination points to support a minimum of 40‑ampere, 208 or 240-volt branch circuits, and electrical panel capacity suitable to provide level 2 charging consistent with an alternating current level 2 charging station, as defined in section 269-72."
SECTION 3. (a) The Hawaii state energy office, in consultation with the department of accounting and general services and department of transportation, shall survey existing state facilities statewide that include parking, including but not limited to state-owned parking lots that serve a state facility, regardless of whether the lots are physically attached to a building, and prioritize retrofitting these state facilities in accordance with readily available information, including location, expected future demand for charging, estimated costs for retrofits of parking stalls, other make‑ready work, other planned improvements that would allow for electric vehicle charger-ready retrofit work to be performed at the same time, retrofitting for level 1 or level 3 charging at high-priority sites where appropriate, and other factors that the Hawaii state energy office deems relevant.
(b) The Hawaii state energy office shall submit a report to the legislature no later than twenty days prior to the convening of the regular session of 2026. The report shall include the results of the survey conducted pursuant to subsection (a), identifying between four to ten high-priority state facilities to be retrofitted to include electric vehicle charging infrastructure.
SECTION 4. It shall be the goal of the State to retrofit state facilities to be electric vehicle charger-ready.
SECTION 5. There is appropriated out of the general revenues of the State of Hawaii the sum of $ or so much thereof as may be necessary for fiscal year 2026-2027 to conduct detailed cost assessments to determine the cost to install, or contract for the installation of, retrofits and electric vehicle charging systems at the high-priority state facilities identified pursuant to section 3 of this Act and to perform, or contract for, these installations.
The sum appropriated shall be expended by the Hawaii state energy office for the purposes of this Act.
SECTION 6. New statutory material is underscored.
SECTION 7. This Act shall take effect on July 1, 3000.
Report Title:
HSEO; DOT; DAGS; Electric Vehicle Charging Infrastructure; State Buildings; Retrofitting; Appropriation
Description:
Requires the design of all new state building construction where parking is to be included to provide that a number of the parking stalls, as determined by the Department of Accounting and General Services, shall be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (SD2)
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
|
HOUSE OF REPRESENTATIVES |
H.B. NO. |
344 |
|
THIRTY-THIRD LEGISLATURE, 2025 |
H.D. 1 |
|
|
STATE OF HAWAII |
S.D. 1 |
|
|
|
|
|
|
|
||
|
|
||
A BILL FOR AN ACT
RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The legislature finds that the adoption of electric vehicles in the State continues to grow at increasing rates, with electric vehicles accounting for fifteen per cent of all new car sales in 2024, up 11.5 per cent from the year prior. There is a need for charging infrastructure to support this growth and ensure that there is an equitable transition to clean transportation.
The legislature further finds that providing electric vehicle charging options at workplaces is beneficial for several reasons. Workplace charging provides options for people who may not be able to charge at home--typically renters, those who live in apartments, and low- and moderate-income families--the opportunity to participate in the savings and other benefits of owning an electric vehicle. Workplace charging also encourages daytime charging, which benefits the grid by shifting energy use from peak evening hours to daytime hours, when energy is cheaper and cleaner.
Therefore, the legislature finds that there is a need for more workplace charging and that the State should expand workplace charging availability in state facilities.
The purpose of this Act is to:
(1) Require the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger‑ready;
(2) Require the Hawaii state energy office to conduct a survey and identify certain high-priority state facilities that include parking, including state-owned parking lots that serve a state facility, regardless of whether they are attached to the facility, to be retrofitted to include electric vehicle charging infrastructure;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the Hawaii state energy office to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
SECTION 2. Section 107-27, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows:
"(d) Beginning July 1, 2023, where feasible and cost-effective, the design of all new state building construction shall:
(1) Maximize energy and water efficiency measures;
(2) Maximize energy generation potential; and
(3) Use building materials that reduce the carbon footprint of the project.
Beginning July 1, 2026, the design of all new state building construction where parking is to be included shall provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready.
For the purposes of this subsection, "electric vehicle charger-ready" means having sufficient wiring conduits, raceways, and termination points to support a minimum of 40‑ampere, 208 or 240-volt branch circuits, and electrical panel capacity suitable to provide level 2 charging consistent with an alternating current level 2 charging station, as defined in section 269-72."
SECTION 3. (a) The Hawaii state energy office, in consultation with the department of accounting and general services and department of transportation, shall survey existing state facilities statewide that include parking, including but not limited to state-owned parking lots that serve a state facility, regardless of whether the lots are physically attached to a building, and prioritize retrofitting these state facilities in accordance with readily available information, including location, expected future demand for charging, estimated costs for retrofits of parking stalls, other make-ready work, other planned improvements that would allow for electric vehicle charger-ready retrofit work to be performed at the same time, retrofitting for level 1 or level 3 charging at high-priority sites where appropriate, and other factors that the Hawaii state energy office deems relevant.
(b) The Hawaii state energy office shall submit a report to the legislature no later than twenty days prior to the convening of the regular session of 2026. The report shall include the results of the survey conducted pursuant to subsection (a), identifying between four to ten high-priority state facilities to be retrofitted to include electric vehicle charging infrastructure.
SECTION 4. It shall be the goal of the State to retrofit state facilities to be electric vehicle charger-ready.
SECTION 5. There is appropriated out of the general revenues of the State of Hawaii the sum of $ or so much thereof as may be necessary for fiscal year 2026-2027 to conduct detailed cost assessments to determine the cost to install, or contract for the installation of, retrofits and electric vehicle charging systems at the high-priority state facilities identified pursuant to section 3 of this Act and to perform, or contract for, these installations.
The sum appropriated shall be expended by the Hawaii state energy office for the purposes of this Act.
SECTION 6. New statutory material is underscored.
SECTION 7. This Act shall take effect on July 1, 3000.
Report Title:
HSEO; DOT; DAGS; Electric Vehicle Charging Infrastructure; State Buildings; Retrofitting; Appropriation
Description:
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (SD1)
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
|
HOUSE OF REPRESENTATIVES |
H.B. NO. |
344 |
|
THIRTY-THIRD LEGISLATURE, 2025 |
H.D. 1 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
|
|
||
|
|
||
A BILL FOR AN ACT
RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The legislature finds that the adoption of electric vehicles in the State continues to grow at increasing rates, with electric vehicles accounting for fifteen per cent of all new car sales in 2024, up 11.5 per cent from the year prior. There is a need for charging infrastructure to support this growth and ensure that there is an equitable transition to clean transportation.
The legislature further finds that providing electric vehicle charging options at workplaces is beneficial for several reasons. Workplace charging provides options for people who may not be able to charge at home--typically renters, those who live in apartments, and low- and moderate-income families--the opportunity to participate in the savings and other benefits of owning an electric vehicle. Workplace charging also encourages daytime charging, which benefits the grid by shifting energy use from peak evening hours to daytime hours, when energy is cheaper and cleaner.
Therefore, the legislature finds that there is a need for more workplace charging and that the State should expand workplace charging availability in state facilities.
The purpose of this Act is to:
(1) Require the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger‑ready;
(2) Require the Hawaii state energy office to conduct a survey and identify certain high-priority state facilities that include parking to be retrofitted to include electric vehicle charging infrastructure;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the Hawaii state energy office to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
SECTION 2. Section 107-27, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows:
"(d) Beginning July 1, 2023, where feasible and cost-effective, the design of all new state building construction shall:
(1) Maximize energy and water efficiency measures;
(2) Maximize energy generation potential; and
(3) Use building materials that reduce the carbon footprint of the project.
Beginning July 1, 2026, the design of all new state building construction where parking is to be included shall provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready.
For the purposes of this subsection, "electric vehicle charger-ready" means having sufficient wiring conduits, raceways, and termination points to support a minimum of 40‑ampere, 208 or 240-volt branch circuits, and electrical panel capacity suitable to provide Level 2 charging consistent with an alternating current Level 2 charging station, as defined in section 269-72."
SECTION 3. (a) The Hawaii state energy office, in consultation with the department of accounting and general services and department of transportation, shall survey existing state facilities statewide that include parking and prioritize retrofitting these state facilities in accordance with readily available information, including location, expected future demand for charging, estimated costs for retrofits of parking stalls, other make-ready work, other planned improvements that would allow for electric vehicle charger-ready retrofit work to be performed at the same time, and other factors that the Hawaii state energy office deems relevant.
(b) The Hawaii state energy office shall submit a report to the legislature no later than twenty days prior to the convening of the regular session of 2026. The report shall include the results of the survey conducted pursuant to subsection (a), identifying between four to ten high-priority state facilities to be retrofitted to include electric vehicle charging infrastructure.
SECTION 4. It shall be the goal of the State to retrofit state facilities to be electric vehicle charger-ready.
SECTION 5. There is appropriated out of the general revenues of the State of Hawaii the sum of $ or so much thereof as may be necessary for fiscal year 2026-2027 to conduct detailed cost assessments to determine the cost to install, or contract for the installation of, retrofits and electric vehicle charging systems at the high-priority state facilities identified pursuant to section 3 of this Act and to perform, or contract for, these installations.
The sum appropriated shall be expended by the Hawaii state energy office for the purposes of this Act.
SECTION 6. New statutory material is underscored.
SECTION 7. This Act shall take effect on July 1, 3000.
Report Title:
HSEO; DOT; DAGS; Electric Vehicle Charging Infrastructure; State Buildings; Retrofitting; Appropriation
Description:
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds. Effective 7/1/3000. (HD1)
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
|
HOUSE OF REPRESENTATIVES |
H.B. NO. |
344 |
|
THIRTY-THIRD LEGISLATURE, 2025 |
|
|
|
STATE OF HAWAII |
|
|
|
|
|
|
|
|
||
|
|
||
A BILL FOR AN ACT
RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The legislature finds that the adoption of electric vehicles in the State continues to grow at increasing rates, with electric vehicles accounting for fifteen per cent of all new car sales in 2024, up 11.5 per cent from the year prior. There is a need for charging infrastructure to support this growth and ensure that there is an equitable transition to clean transportation.
The legislature further finds that providing electric vehicle charging options at workplaces is beneficial for several reasons. Workplace charging provides options for people who may not be able to charge at home--typically renters, those who live in apartments, and low- and moderate-income families--the opportunity to participate in the savings and other benefits of owning an electric vehicle. Workplace charging also encourages daytime charging, which benefits the grid by shifting energy use from peak evening hours to daytime hours, when energy is cheaper and cleaner.
Therefore, the legislature finds that there is a need for more workplace charging and that the State should expand workplace charging availability in state facilities.
The purpose of this Act is to:
(1) Require the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger‑ready;
(2) Require the Hawaii state energy office to conduct a survey and identify certain high-priority state facilities that include parking to be retrofitted to include electric vehicle charging infrastructure;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the department of accounting and general services to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
SECTION 2. Section 107-27, Hawaii Revised Statutes, is amended by amending subsection (d) to read as follows:
"(d) Beginning July 1, 2023, where feasible and cost-effective, the design of all new state building construction shall:
(1) Maximize energy and water efficiency measures;
(2) Maximize energy generation potential; and
(3) Use building materials that reduce the carbon footprint of the project.
Beginning July 1, 2025, the design of all new state building construction where parking is to be included shall provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready.
For the purposes of this subsection, "electric vehicle charger-ready" means having sufficient wiring conduits, raceways, and termination points to support a minimum of 40‑ampere, 208 or 240-volt branch circuits, and electrical panel capacity suitable to provide Level 2 charging consistent with an alternating current Level 2 charging station, as defined in section 269-72."
SECTION 3. (a) The Hawaii state energy office, in consultation with the department of accounting and general services and department of transportation, shall survey existing state facilities statewide that include parking and prioritize retrofitting these state facilities in accordance with readily available information, including location, expected future demand for charging, estimated costs for retrofits of parking stalls, other make-ready work, other planned improvements that would allow for electric vehicle charger-ready retrofit work to be performed at the same time, and other factors that the Hawaii state energy office deems relevant.
(b) The Hawaii state energy office shall submit a report to the legislature no later than twenty days prior to the convening of the regular session of 2026. The report shall include the results of the survey conducted pursuant to subsection (a), identifying between four to ten high-priority state facilities to be retrofitted to include electric vehicle charging infrastructure.
SECTION 4. It shall be the goal of the State to retrofit state facilities to be electric vehicle charger-ready.
SECTION 5. There is appropriated out of the general revenues of the State of Hawaii the sum of $300,000 or so much thereof as may be necessary for fiscal year 2025-2026 and the same sum or so much thereof as may be necessary for fiscal year 2026-2027 to conduct detailed cost assessments to determine the cost to install, or contract for the installation of, retrofits and electric vehicle charging systems at the high-priority state facilities identified pursuant to section 3 of this Act and to perform, or contract for, these installations.
The sums appropriated shall be expended by the department of accounting and general services for the purposes of this Act.
SECTION 6. New statutory material is underscored.
SECTION 7. This Act shall take effect on July 1, 2025.
|
INTRODUCED BY: |
_____________________________ |
|
|
|
Report Title:
HSEO; DOT; DAGS; Electric Vehicle Charging Infrastructure; State Buildings; Retrofitting; Appropriation
Description:
Requires the design of all new state building construction where parking is to be included to provide that at least twenty-five per cent of parking stalls be electric vehicle charger-ready. Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities. Establishes a goal of the State to retrofit state facilities to be electric vehicle charger-ready. Requires a report to the Legislature. Appropriates funds.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.
|
Date
|
Status
|
|---|---|
| Apr 23, 2026 | Received notice of appointment of House conferees (Hse. Com. No. 817). |
| Apr 23, 2026 | House Conferees Appointed: Lowen, Perruso Co-Chairs; Alcos. |
| Apr 2, 2026 | Received notice of the discharge of all House Conferees (Hse. Com. No. 457). |
| Apr 1, 2026 | House Conferee(s) discharged. |
| Mar 20, 2026 | Received notice of all Senate conferees being discharged (Sen. Com. No. 409). |
| Mar 20, 2026 | Senate Conferee(s) discharged. |
| Dec 8, 2025 | Carried over to 2026 Regular Session. |
| Apr 25, 2025 | Conference Committee Meeting will reconvene on Friday, 04-25-25 at 5:55PM in Conference Room 325. |
| Apr 25, 2025 | Conference Committee Meeting will reconvene on Friday, 04-25-25 at 5:10PM in Conference Room 325. |
| Apr 25, 2025 | Conference Committee Meeting will reconvene on Friday, 04-25-25 at 4:05PM in Conference Room 325. |
| Apr 24, 2025 | Received notice of Senate conferees (Sen. Com. No. 875). |
| Apr 24, 2025 | Bill scheduled for Conference Committee Meeting on Friday, 04-25-25 11:15AM in conference room 325. |
| Apr 24, 2025 | Senate Conferees Appointed: Wakai Chair; McKelvey, DeCoite Co-Chairs; Fevella. |
| Apr 23, 2025 | Received notice of appointment of House conferees (Hse. Com. No. 804). |
| Apr 22, 2025 | House Conferees Appointed: Lowen, Takenouchi Co-Chairs; Kusch, Perruso, Alcos. |
| Apr 11, 2025 | Received notice of disagreement (Hse. Com. No. 704). |
| Apr 10, 2025 | House disagrees with Senate amendment (s). |
| Apr 8, 2025 | Returned from Senate (Sen. Com. No. 621) in amended form (SD 2). |
| Apr 8, 2025 | Report Adopted; Passed Third Reading, as amended (SD 2). Ayes, 24; Aye(s) with reservations: none. Noes, 1 (Senator(s) Awa). Excused, 0 (none). Transmitted to House. |
| Apr 4, 2025 | 48 Hrs. Notice 04-08-25. |
| Apr 4, 2025 | Reported from WAM (Stand. Com. Rep. No. 1833) with recommendation of passage on Third Reading, as amended (SD 2). |
| Apr 4, 2025 | The committee(s) on WAM recommend(s) that the measure be PASSED, WITH AMENDMENTS. The votes in WAM were as follows: 12 Aye(s): Senator(s) Dela Cruz, Moriwaki, Aquino, DeCoite, Elefante, Hashimoto, Inouye, Kanuha, Kidani, Kim, Wakai, Fevella; Aye(s) with reservations: none ; 0 No(es): none; and 1 Excused: Senator(s) Lee, C.. |
| Apr 2, 2025 | The committee(s) on WAM will hold a public decision making on 04-04-25 10:46AM; Conference Room 211 & Videoconference. |
| Mar 21, 2025 | Report adopted; Passed Second Reading, as amended (SD 1) and referred to WAM. |
| Mar 21, 2025 | Reported from EIG/GVO (Stand. Com. Rep. No. 1248) with recommendation of passage on Second Reading, as amended (SD 1) and referral to WAM. |
| Mar 18, 2025 | The committee(s) on GVO recommend(s) that the measure be PASSED, WITH AMENDMENTS. The votes in GVO were as follows: 3 Aye(s): Senator(s) McKelvey, Gabbard; Aye(s) with reservations: Senator(s) San Buenaventura ; 0 No(es): none; and 2 Excused: Senator(s) Moriwaki, Fevella. |
| Mar 18, 2025 | The committee(s) on EIG recommend(s) that the measure be PASSED, WITH AMENDMENTS. The votes in EIG were as follows: 3 Aye(s): Senator(s) Wakai, DeCoite; Aye(s) with reservations: Senator(s) Richards ; 0 No(es): none; and 2 Excused: Senator(s) Chang, Fevella. |
| Mar 13, 2025 | The committee(s) on EIG/GVO has scheduled a public hearing on 03-18-25 3:00PM; Conference Room 016 & Videoconference. |
| Mar 10, 2025 | Re-Referred to EIG/GVO, WAM. |
| Mar 4, 2025 | Referred to GVO/EIG, WAM. |
| Feb 28, 2025 | Passed First Reading. |
| Feb 28, 2025 | Received from House (Hse. Com. No. 14). |
| Feb 27, 2025 | Passed Third Reading with none voting aye with reservations; Representative(s) Garcia, Kong, Muraoka, Shimizu voting no (4) and Representative(s) Cochran, Pierick, Templo, Ward excused (4). Transmitted to Senate. |
| Feb 27, 2025 | Reported from FIN (Stand. Com. Rep. No. 880), recommending passage on Third Reading. |
| Feb 20, 2025 | The committee on FIN recommend that the measure be PASSED, UNAMENDED. The votes were as follows: 14 Ayes: Representative(s) Yamashita, Takenouchi, Grandinetti, Holt, Hussey, Keohokapu-Lee Loy, Kitagawa, Kusch, Lamosao, Lee, M., Miyake, Morikawa, Templo, Reyes Oda; Ayes with reservations: none; Noes: none; and 2 Excused: Representative(s) Alcos, Ward. |
| Feb 18, 2025 | Bill scheduled to be heard by FIN on Thursday, 02-20-25 12:00PM in House conference room 308 VIA VIDEOCONFERENCE. |
| Feb 12, 2025 | Passed Second Reading as amended in HD 1 and referred to the committee(s) on FIN with Representative(s) Shimizu voting aye with reservations; Representative(s) Garcia, Pierick voting no (2) and Representative(s) Cochran, Sayama, Ward excused (3). |
| Feb 12, 2025 | Reported from EEP (Stand. Com. Rep. No. 503) as amended in HD 1, recommending passage on Second Reading and referral to FIN. |
| Feb 6, 2025 | The committee on EEP recommend that the measure be PASSED, WITH AMENDMENTS. The votes were as follows: 5 Ayes: Representative(s) Lowen, Perruso, Kahaloa, Kusch, Quinlan; Ayes with reservations: none; Noes: none; and 1 Excused: Representative(s) Ward. |
| Jan 29, 2025 | Bill scheduled to be heard by EEP on Thursday, 02-06-25 9:00AM in House conference room 325 VIA VIDEOCONFERENCE. |
| Jan 28, 2025 | Re-referred to EEP, FIN, referral sheet 6 |
| Jan 21, 2025 | Referred to EEP, LAB, FIN, referral sheet 1 |
| Jan 17, 2025 | Introduced and Pass First Reading. |
| Jan 16, 2025 | Pending introduction. |
|
Date
|
Description
|
Location
|
Votes
|
|
|---|---|---|---|---|
| Apr 8, 2025 | Third Reading | Senate Floor |
Passed |
|
| Apr 4, 2025 | The committee(s) on WAM recommend(s) that the measure be PASSED, WITH AMENDMENTS | Senate Standing Committee on Ways and Means |
Passed |
|
| Mar 18, 2025 | The committee(s) on GVO recommend(s) that the measure be PASSED, WITH AMENDMENTS | Senate Standing Committee on Government Operations |
Passed |
|
| Mar 18, 2025 | The committee(s) on EIG recommend(s) that the measure be PASSED, WITH AMENDMENTS | Senate Standing Committee on Energy and Intergovernmental Affairs |
Passed |
|
| Feb 27, 2025 | Third Reading | House Floor |
Passed |
|
| Feb 20, 2025 | The committee on FIN recommend that the measure be PASSED, UNAMENDED | House Standing Committee on Finance |
Passed |
|
| Feb 6, 2025 | The committee on EEP recommend that the measure be PASSED, WITH AMENDMENTS | House Standing Committee on Energy & Environmental Protection |
Passed |
This list shows positions taken on this bill by organizations on the date displayed, which is linked to the original source.
Positions by individuals are not included.
|
Organization
|
Position
|
Date
|
|---|---|---|
| 350Hawaii.org | *** Support | Apr 3, 2025 |
| Alliance for Automotive Innovation | *** Support | Apr 3, 2025 |
| Carbon Cashback Hawaii | *** Support | Apr 3, 2025 |
| Carbon Cashback Hawaii | ** Support | |
| CarbonCashback Hawaii | *** Support | Mar 18, 2025 |
| Climate Change Mitigation and Adaptation Commission | *** Support | Apr 3, 2025 |
| Climate Future Forum | ** Support | |
| Climate Protectors Hawai‘i | *** Support | Apr 3, 2025 |
| Coalition Earth | ** Support | |
| Department of Transportation | ** Support | |
| Department of Accounting and General Services | *** Support | Apr 3, 2025 |
| Department of Transportation | ** Support | |
| Environmental Caucus of the Democratic Party of Hawaiʻi | ** Support | |
| Green Party of Hawaiʻi | ** Support | |
| Hawaii Department of Transportation | *** Support | Apr 3, 2025 |
| Hawaii Electric Vehicle Association | *** Support | Apr 3, 2025 |
| Hawaiian Electric | *** Support | Apr 3, 2025 |
| Hawaiʻi Workers Center | *** Support | Feb 6, 2025 |
| Hawai‘i State Energy Office | *** Support | Apr 3, 2025 |
| Kauai Climate Action Coalition | ** Support | |
| Kauai EV | ** Support | |
| Oahu Metropolitan Planning Organization | *** Support | Apr 3, 2025 |
| RERides EV, LLC | ** Support | |
| Sierra Club of Hawaiʻi | *** Support | Feb 6, 2025 |
| Ulupono Initiative | *** Support | Apr 3, 2025 |
STAND. COM. REP. NO. 1833
Honolulu, Hawaii
RE: H.B. No. 344
H.D. 1
S.D. 2
Honorable Ronald D. Kouchi
President of the Senate
Thirty-Third State Legislature
Regular Session of 2025
State of Hawaii
Sir:
Your Committee on Ways and Means, to which was referred H.B. No. 344, H.D. 1, S.D. 1, entitled:
"A BILL FOR AN ACT RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE,"
begs leave to report as follows:
The purpose and intent of this measure is to improve the State's electric vehicle charging infrastructure.
More specifically, the measure:
(1) Requires the design of all new state buildings where parking is to be included to make at least twenty-five percent of the parking stalls electric vehicle charger‑ready;
(2) Requires the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state buildings that have parking facilities to be retrofitted to include electric vehicle chargers;
(3) Establishes as a goal of the State the retrofitting of state facilities to be electric vehicle charger-ready; and
(4) Appropriates moneys to the Hawaii State Energy Office to assess the costs of, and to install at high-priority state facilities, retrofits and electric vehicle charger systems.
Your Committee received written comments in support of this measure from the Department of Transportation, Department of Accounting and General Services, Climate Change Mitigation and Adaptation Commission, Hawaii State Energy Office, Carbon Cashback Hawaii, Hawaii Electric Vehicle Association, Climate Protectors Hawaii, Alliance for Automotive Innovation, 350 Hawaii, Hawaiian Electric, Ulupono Initiative, Oahu Metropolitan Planning Organization, and nine individuals.
Your Committee
finds that many residents who rent their homes, especially residents of
multi-dwelling buildings, lack
at-home access to electric vehicle chargers.
Developing the infrastructure to allow workers and visitors to charge at
state facilities will support the State's clean energy goals by removing a significant
barrier to electric vehicle use.
Your Committee has amended this measure by specifying that, in the design of all new state building construction, beginning July 1, 2026, the Department of Accounting and General Services shall determine the number of parking stalls that are required to be electric vehicle charger-ready.
As affirmed by the record of votes of the members of your Committee on Ways and Means that is attached to this report, your Committee is in accord with the intent and purpose of H.B. No. 344, H.D. 1, S.D. 1, as amended herein, and recommends that it pass Third Reading in the form attached hereto as H.B. No. 344, H.D. 1, S.D. 2.
Respectfully submitted on behalf of the members of the Committee on Ways and Means,
|
|
|
________________________________ DONOVAN M. DELA CRUZ, Chair |
|
|
|
|
STAND. COM. REP. NO. 1248
Honolulu, Hawaii
RE: H.B. No. 344
H.D. 1
S.D. 1
Honorable Ronald D. Kouchi
President of the Senate
Thirty-Third State Legislature
Regular Session of 2025
State of Hawaii
Sir:
Your Committees on Energy and Intergovernmental Affairs and Government Operations, to which was referred H.B. No. 344, H.D. 1, entitled:
"A BILL FOR AN ACT RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE,"
beg leave to report as follows:
The purpose and intent of this measure is to:
(1) Require the design of all new state building construction where parking is to be included to provide that at least twenty-five percent of parking stalls be electric vehicle charger-ready;
(2) Require the Hawaii State Energy Office, in consultation with the Department of Accounting and General Services and Department of Transportation, to conduct a survey and identify certain high-priority state facilities;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready;
(4) Require a report to the Legislature; and
(5) Appropriate funds.
Your Committees received testimony in support of this measure from the Department of Accounting and General Services, Hawaii State Energy Office, Hawaiʻi Climate Change Mitigation and Adaptation Commission, Oahu Metropolitan Planning Organization, Hawaii Electric Vehicle Association, Carbon Cashback Hawaii, Kauai Climate Action Coalition, Ulupono Initiative, Climate Protectors Coalition, 350Hawaii.org, Hawaiian Electric, Coalition Earth, Kauai EV, Alliance for Automotive Innovation, and twenty-seven individuals.
Your Committees received comments on this measure from the Disability and Communication Access Board.
Your Committees find that the adoption of electric vehicles in Hawaii has grown in recent years and is expected to continue to grow at increasing rates. Your Committees note that increasing electric vehicle use reduces carbon emissions from ground transportation and helps to achieve the State's goals of reducing carbon emissions to fifty percent by 2030 and establishing a net-negative carbon economy by 2045. However, your Committees recognize that there is a lack of adequate charging infrastructure in the State. Your Committees further find that workplace charging can shift charging demand from peak hours, typically in the early evening, to times during the day when renewable energy is more economical and plentiful. Your Committees believe that the State should lead by example by expanding workplace charging availability in state facilities. This measure addresses this need by establishing certain requirements and goals for state facilities to provide electric vehicle charging infrastructure, ensuring greater equity for electric vehicle charging infrastructure to support the State's clean energy goals.
According to testimony received by your Committees, expanding the scope of the survey of existing state facilities that include parking to also include state-owned parking lots that serve a state facility, regardless of whether the lots are physically attached to a building, would better support the goal of increasing electric vehicle charging availability statewide. Your Committees further note that, although level 2 charging stations are the preferred standard for new construction, allowing the installation of level 1 and level 3 charging infrastructure when retrofitting high-priority sites could provide cost effective and larger charging need capabilities where needed. Amendments to this measure are therefore necessary to address these matters.
Accordingly, your Committees have amended this measure by:
(1) Requiring the Hawaii State Energy Office to:
(A) Include in its survey of existing state facilities, state-owned parking lots that serve a state facility, regardless of whether the lots are physically attached to a building; and
(B) Consider retrofitting high-priority sites with level 1 or level 3 charging, where appropriate;
(2) Amending section 1 to reflect its amended purpose; and
(3) Making technical, nonsubstantive amendments for the purposes of clarity and consistency.
As affirmed by the records of votes of the members of your Committees on Energy and Intergovernmental Affairs and Government Operations that are attached to this report, your Committees are in accord with the intent and purpose of H.B. No. 344, H.D. 1, as amended herein, and recommend that it pass Second Reading in the form attached hereto as H.B. No. 344, H.D. 1, S.D. 1, and be referred to your Committee on Ways and Means.
Respectfully submitted on behalf of the members of the Committees on Energy and Intergovernmental Affairs and Government Operations,
|
________________________________ ANGUS L.K. MCKELVEY, Chair |
|
________________________________ GLENN WAKAI, Chair |
|
|
|
|
STAND. COM. REP. NO. 880
Honolulu, Hawaii
, 2025
RE: H.B. No. 344
H.D. 1
Honorable Nadine K. Nakamura
Speaker, House of Representatives
Thirty-Third State Legislature
Regular Session of 2025
State of Hawaii
Madame:
Your Committee on Finance, to which was referred H.B. No. 344, H.D. 1, entitled:
"A BILL FOR AN ACT RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE,"
begs leave to report as follows:
The purpose of this measure is to:
(1) Beginning July 1, 2026, require the design of all new state building construction where parking is to be included to have at least twenty-five percent of parking stalls be electric vehicle charger‑ready;
(2) Require the Hawaii State Energy Office to conduct a survey and identify certain high-priority state facilities that include parking that can be retrofitted to include electric vehicle charging infrastructure and report to the Legislature;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the Hawaii State Energy Office to conduct a cost assessment and perform or contract for the installation of retrofits and electric vehicle charging systems at high-priority state facilities.
Your Committee received testimony in support of this measure from the Department of Accounting and General Services; Department of Transportation; Climate Protectors Hawaiʻi; Coalition Earth; 350Hawaii.org; Hawaii Electric Vehicle Association; Climate Future Forum; Hawaiian Electric; Ulupono Initiative; Alliance for Automotive Innovation; Environmental Caucus of the Democratic Party of Hawaiʻi; and three individuals. Your Committee received comments on this measure from the Hawaiʻi Climate Change Mitigation & Adaptation Commission; Hawaiʻi State Energy Office; Disability and Communication Access Board; and Oahu Metropolitan Planning Organization.
As affirmed by the record of votes of the members of your Committee on Finance that is attached to this report, your Committee is in accord with the intent and purpose of H.B. No. 344, H.D. 1, and recommends that it pass Third Reading.
Respectfully submitted on behalf of the members of the Committee on Finance,
|
|
|
____________________________ KYLE T. YAMASHITA, Chair |
|
|
|
|
STAND. COM. REP. NO. 503
Honolulu, Hawaii
, 2025
RE: H.B. No. 344
H.D. 1
Honorable Nadine K. Nakamura
Speaker, House of Representatives
Thirty-Third State Legislature
Regular Session of 2025
State of Hawaii
Madame:
Your Committee on Energy & Environmental Protection, to which was referred H.B. No. 344 entitled:
"A BILL FOR AN ACT RELATING TO ELECTRIC VEHICLE CHARGING INFRASTRUCTURE,"
begs leave to report as follows:
The purpose of this measure is to:
(1) Require the design of all new state building construction where parking is to be included to provide that at least twenty-five percent of parking stalls be electric vehicle charger‑ready;
(2) Require the Hawaii State Energy Office to conduct a survey and identify certain high-priority state facilities that include parking to be retrofitted to include electric vehicle charging infrastructure;
(3) Establish a goal of the State to retrofit state facilities to be electric vehicle charger-ready; and
(4) Appropriate funds to the Department of Accounting and General Services to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
Your Committee received testimony in support of this measure from the Department of Transportation; Department of Accounting and General Services; Hawaii State Energy Office; Oahu Metropolitan Planning Organization; Hawaiian Electric; Ulupono Initiative; Climate Protectors Hawaiʻi; 350Hawaii.org; Coalition Earth; Green Party of Hawaiʻi; Environmental Caucus of the Democratic Party of Hawaiʻi; Kauai Climate Action Coalition; RERides EV, LLC; Alliance for Automotive Innovation; and numerous individuals.
Your Committee finds that electric vehicle usage has greatly increased in recent years, with electric vehicles accounting for fifteen percent of all new car sales in 2024. Your Committee further finds that the State must support the transition to electric vehicles by ensuring that adequate charging infrastructure is available. This measure addresses this need by establishing certain requirements and goals for state facilities to provide electric vehicle charging infrastructure.
Your Committee has amended this measure by:
(1) Changing the start date on which all new state building construction must meet certain electric vehicle charging requirements to July 1, 2026;
(2) Changing the appropriation to an unspecified amount and removing the appropriation for fiscal year 2025-2026;
(3) Changing the expending entity to the Hawaii State Energy Office;
(4) Changing the effective date to July 1, 3000, to encourage further discussion; and
(5) Making technical, nonsubstantive amendments for the purposes of clarity, consistency, and style.
Your Committee respectfully requests your Committee on Finance, should it deliberate on this measure, to consider an appropriation amount of $300,000 for fiscal year 2026-2027 to assess the costs of, and install, retrofits and electric vehicle charging systems at high-priority state facilities.
As affirmed by the record of votes of the members of your Committee on Energy & Environmental Protection that is attached to this report, your Committee is in accord with the intent and purpose of H.B. No. 344, as amended herein, and recommends that it pass Second Reading in the form attached hereto as H.B. No. 344, H.D. 1, and be referred to your Committee on Finance.
Respectfully submitted on behalf of the members of the Committee on Energy & Environmental Protection,
|
|
|
____________________________ NICOLE E. LOWEN, Chair |
|
|
|
|
|
Date
|
Testimony PDF
|
|---|---|
| Apr 3, 2025 | HB344_SD1_TESTIMONY_WAM_04-04-25_.PDF |
| Mar 18, 2025 | HB344_HD1_TESTIMONY_EIG-GVO_03-18-25_.PDF |
| Feb 20, 2025 | HB344_HD1_TESTIMONY_FIN_02-20-25_.PDF |
| Feb 6, 2025 | HB344_TESTIMONY_EEP_02-06-25_.PDF |
Discussed in Hearing
Conference Committee
Conference Committee
Conference Committee
Senate Standing Committee on Government Operations
Senate Standing Committee on Energy and Intergovernmental Affairs
House Standing Committee on Finance
House Standing Committee on Energy & Environmental Protection
Bill Author